Project Type( Urban /Industrial Infrastructure )
Project Code | Start and Complete Date | Project Name | Client | Location | Project Cost | Fee | Services | Further Details | Gallery |
3 |
6/1/2022 10/1/2022 |
Hubco Thar Energy Limited Coal Fired Power Plant Detail Design and construction drawings for storm water drain and rainwater disposal arrangement |
Berkeley Associates |
Thar, Pakistan |
To be Estimated |
US$6,400 |
| | |
4 |
6/1/2022 10/1/2022 |
Hubco Thal Nova Coal Fired Power Plant Detail Design and construction drawings for storm water drain and rainwater disposal arrangement for |
Berkeley Associates |
Thar, Pakistan |
To be Estimated |
US$4,000 |
| | |
8 |
6/1/2004 10/1/2004 |
Hydrological Studies for Ash Dumping Area of Shoaiba Power Station, Saudi Arabia |
Rashid Geotechnical and Materials Engineers (RGME) ;P.O.Box 15833, Riyadh 11454, Riyadh, Saudi Arabia |
Western Region, Saudi Arabia |
N.A |
US $ 520 |
| | |
38 |
May 2024 Dec 2024 |
Construction Supervision of Optimization of Bunda Water Supply Network and Packaged Treatment Plant and Priority Efficiency Improvement Measures for LWB’s Treatment Works I and II |
Pamodzi Consulting Limited |
Lilongwe |
US$ 2.7 million |
US$ 25,000 |
| | |
5 |
12/1/2021 9/1/2022 |
Infrastructure Development for Multan Industrial Estate Commercial Area 2 |
Kashif Aslam & Associates; Punjab Industrial Estate Development Management Company |
Punjab, Pakistan |
To be Estimated |
US$8,000 |
| | |
6 |
2/1/2013 12/1/2013 |
Infrastructure Design Support Services for Shahbaz Airbase |
Sub-Consultant to Kashif Aslam & Associates |
Pakistan |
US$ 156 million |
US$ 25,000 |
| | |
2 |
2/1/2022 12/1/202 |
Development of additional connecting road between US Apparell Unit 3 to Kalamkar Road along with stormwater drain and pumping station |
Sub-Consultant to Kashif Aslam & Associates |
Punjab, Pakistan |
To be Estimated |
US$ 1,300 |
| | |
7 |
3/1/2011 7/1/2011 |
Master Planning of Karachi Education City |
Halcrow Pakistan |
Karachi, Pakistan |
N.A. |
US$ 14,000 |
| | |
1 |
8/1/2013 8/1/2015 |
Infrastructure program management services for Jinnah Post Graduate Medical Maternity Ward Construction |
US AID through Kashif Aslam & Associates and Izhar Construction Pvt Ltd |
Karachi, Pakistan |
US$ 3.6 million |
US$ 84,000 |
| | |